INSTALLATION OF A NEW MEDIUM VOLTAGE SWITCHGEAR TROUGH THE ELEVATOR SHAFT

On Monday June 11 and Tuesday June 12, the Deba staff installed new medium voltage switchgear for the new  Project Redevco in Elsene.

The specificity of this project was that the medium voltage cubicles and the transformer of 1000 kVA, with a weight of 2.6T, had to be installed one floor lower, and to do this, the equipment had to pass through the elevator shaft.

Pictures shows how the medium voltage cubicles and the transformer were first lifted on a platform, to be later attached to the tower crane, and so through the roof of the elevator shaft, lowered one floor lower.
A real craftsman’s work!